Project Management - Time Management Essay

760 Words Feb 1st, 2013 4 Pages
Project Management Time Management

NOTE: Do not use Microsoft Project to create and calculate these values. Do it “by hand” first and then if you would like to experiment with MS Project feel free to do so after you have completed your assignment.
Project #1: Moving across country
Activity A: Get bids on moving company
Activity B: Choose a moving company
Activity C: Go through belongings and decide what to keep and what to sell/give away
Activity D: Prepare for and do a yard sale for unwanted items
Activity E: Give away unwanted items not sold in garage sale
Activity F: Inventory remaining items
Activity G: Pack remaining items
Activity H: Move

Activity Preceding Activities Duration in Days
A Start 9
B
…show more content…
Draw the network diagram for this project (draw by hand and scan or create diagram in PowerPoint, word or excel and import)

2. Which path is the critical path and what is its duration?
Critical Path is A+C+D+G+H+I = 26 days

3. What is the slack for Activity F?

Slack/Float for Activity F is 1
A+B+D+F+H+I = 19 A+C+D+F+H+I = 25 (longest path for F)

Critical Path – longest path for F 26 - 25 = 1 day slack

4. What is the slack for Activity B?

Slack/Float for Activity B is 6

A+B+D+E+H+I = 19 A+B+D+F+H+I = 19 A+B+D+G+H+I = 20 (longest path for B)
Critical Path – longest path for B 26 - 20 = 6 days slack

5. If Activity E now takes four days instead of two days, has the critical path changed?
Yes

6. Based on the information in question 5, what is the new critical path and what is its duration?
*new* Critical Path A+C+D+E+H+I = 27

7. Based on the information in question 5, what is the slack/float